Project Start Date: Mon 01-12-17
Project Finish Date: Mon 02-06-17
ID | WBS | Name | Responsible | Duration | Start_Date | Planned_Finish_Date | Actual_Finish_Date | Predecessors |
---|---|---|---|---|---|---|---|---|
1 | 1.1 | Event Data Model | 77 days? | Mon 01-12-17 | Tue 02-04-02 | NA | ||
2 | 1.1 | Reviews | 70 days | Mon 01-12-17 | Mon 02-03-25 | Mon 02-03-25 | ||
3 | 1.1.1 | Container Classes | M.Frank | 0 days | Mon 01-12-17 | Mon 01-12-17 | Mon 01-12-17 | |
4 | 1.1.2 | Top Level | M.Cattaneo | 0 days | Mon 02-03-04 | Mon 02-03-04 | Mon 02-03-04 | |
5 | 1.1.3 | MCEvent | G.Corti | 0 days | Mon 02-03-04 | Mon 02-03-04 | Mon 02-03-04 | |
6 | 1.1.4 | L0 | 41 days | Mon 02-01-14 | Tue 02-03-12 | Tue 02-03-12 | ||
7 | 1.1.4.1 | L0Calo | O.Callot | 0 days | Mon 02-01-14 | Mon 02-01-14 | Mon 02-01-14 | |
8 | 1.1.4.2 | L0Muon | A.Tsaregorodtsev | 0 days | Tue 02-03-12 | Tue 02-03-12 | Tue 02-03-12 | |
9 | 1.1.4.3 | L0PuVeto | O.Callot | 0 days | Mon 02-01-14 | Mon 02-01-14 | Mon 02-01-14 | |
10 | 1.1.4.4 | L0DU | O.Callot | 0 days | Mon 02-01-14 | Mon 02-01-14 | Mon 02-01-14 | |
11 | 1.1.5 | L1 | O.Callot | 0 days | Mon 02-03-25 | Mon 02-03-25 | Mon 02-03-25 | |
12 | 1.1.6 | VELO | C.Parkes | 0 days | Mon 02-01-14 | Mon 02-01-14 | Mon 02-01-14 | |
13 | 1.1.7 | IT | M.Needham | 0 days | Mon 02-01-28 | Mon 02-01-28 | Mon 02-01-28 | |
14 | 1.1.8 | OT | J.v.Tilburg | 0 days | Mon 02-01-28 | Mon 02-01-28 | Mon 02-01-28 | |
15 | 1.1.9 | Tracking | J.v.Tilburg | 0 days | Mon 02-01-28 | Mon 02-01-28 | Mon 02-01-28 | |
16 | 1.1.10 | RICH | 0 days | Mon 02-02-04 | Mon 02-02-04 | Mon 02-02-04 | ||
17 | 1.1.10.1 | Simulation | A.Presland | 0 days | Mon 02-02-04 | Mon 02-02-04 | Mon 02-02-04 | |
18 | 1.1.10.2 | PID | C.Jones | 0 days | Mon 02-02-04 | Mon 02-02-04 | Mon 02-02-04 | |
19 | 1.1.11 | CALO | V.Belyaev | 0 days | Mon 02-02-18 | Mon 02-02-18 | Mon 02-02-18 | |
20 | 1.1.12 | MUON | 21 days | Mon 02-02-11 | Tue 02-03-12 | Tue 02-03-12 | ||
21 | 1.1.12.1 | Digitisation | A.Satta | 0 days | Mon 02-02-11 | Mon 02-02-11 | Mon 02-02-11 | |
22 | 1.1.12.2 | PID | D.Hutchcroft | 0 days | Tue 02-03-12 | Tue 02-03-12 | Tue 02-03-12 | |
23 | 1.1.13 | Physics | G.Corti | 0 days | Mon 02-01-21 | Mon 02-01-21 | Mon 02-01-21 | |
24 | 1.1.14 | Reference Tables | V.Belyaev | 0 days | Mon 02-02-11 | Mon 02-02-11 | Mon 02-02-11 | |
25 | 1.2 | Implementation | 77 days? | Mon 01-12-17 | Tue 02-04-02 | NA | ||
26 | 1.2.1 | Container Classes | M.Frank | 37 days | Mon 01-12-17 | Tue 02-02-05 | Tue 02-02-05 | 3 |
27 | 1.2.2 | Top Level | M.Cattaneo | 12 days | Mon 02-03-04 | Tue 02-03-19 | Tue 02-03-19 | 4 |
28 | 1.2.3 | MCEvent | G.Corti | 12 days | Mon 02-03-04 | Tue 02-03-19 | Tue 02-03-19 | 5 |
29 | 1.2.4 | L0 | 46 days | Mon 02-01-14 | Mon 02-03-18 | NA | ||
30 | 1.2.4.1 | L0Calo | O.Callot | 13 days | Mon 02-01-14 | Wed 02-01-30 | Wed 02-01-30 | 7 |
31 | 1.2.4.2 | L0Muon | A.Tsaregorodtsev | 5 days | Tue 02-03-12 | Mon 02-03-18 | NA | 8 |
32 | 1.2.4.3 | L0PuVeto | O.Callot | 13 days | Mon 02-01-14 | Wed 02-01-30 | Wed 02-01-30 | 9 |
33 | 1.2.4.4 | L0DU | O.Callot | 13 days | Mon 02-01-14 | Wed 02-01-30 | Wed 02-01-30 | 10 |
34 | 1.2.5 | L1 | O.Callot | 5 days | Mon 02-03-25 | Fri 02-03-29 | NA | 11 |
35 | 1.2.6 | VELO | C.Parkes | 57 days | Mon 02-01-14 | Tue 02-04-02 | NA | 12 |
36 | 1.2.7 | IT | M.Needham | 31 days? | Mon 02-01-28 | Mon 02-03-11 | NA | 13 |
37 | 1.2.8 | OT | J.v.Tilburg | 31 days? | Mon 02-01-28 | Mon 02-03-11 | NA | 14 |
38 | 1.2.9 | Tracking | J.v.Tilburg | 36 days | Mon 02-01-28 | Mon 02-03-18 | NA | 15 |
39 | 1.2.10 | RICH | 36 days | Mon 02-02-04 | Mon 02-03-25 | NA | ||
40 | 1.2.10.1 | Simulation | A.Presland | 36 days | Mon 02-02-04 | Mon 02-03-25 | NA | 17 |
41 | 1.2.10.2 | PID | C.Jones | 36 days | Mon 02-02-04 | Mon 02-03-25 | NA | 18 |
42 | 1.2.11 | CALO | V.Belyaev | 27 days | Mon 02-02-18 | Tue 02-03-26 | Tue 02-03-26 | 19 |
43 | 1.2.12 | MUON | 23 days? | Mon 02-02-11 | Wed 02-03-13 | NA | ||
44 | 1.2.12.1 | Digitisation | A.Satta | 16 days | Mon 02-02-11 | Mon 02-03-04 | NA | 21 |
45 | 1.2.12.2 | PID | D.Hutchcroft | 2 days? | Tue 02-03-12 | Wed 02-03-13 | NA | 22 |
46 | 1.2.13 | ProtoParticles | G.Corti | 5 days | Wed 02-03-27 | Tue 02-04-02 | NA | 38,41,42,45 |
47 | 1.2.14 | Physics | G.Corti | 41 days | Mon 02-01-21 | Mon 02-03-18 | NA | 23 |
48 | 1.2.15 | Reference Tables | V.Belyaev | 21 days | Mon 02-02-11 | Mon 02-03-11 | NA | 24 |
49 | ||||||||
50 | 2 | Algorithms for new model | 63 days? | Wed 02-01-30 | Mon 02-04-29 | NA | 26 | |
51 | 2.1 | L0 | 59 days? | Wed 02-01-30 | Tue 02-04-23 | NA | ||
52 | 2.1.1 | L0Calo Simulation | O.Callot | 0 days? | Wed 02-01-30 | Wed 02-01-30 | Wed 02-01-30 | 30 |
53 | 2.1.2 | L0Muon Simulation | A.Tsaregorodtsev | 1 day? | Tue 02-03-19 | Tue 02-03-19 | NA | 31 |
54 | 2.1.3 | L0PuVeto Simulation | O.Callot | 2 days | Mon 02-04-22 | Tue 02-04-23 | NA | 32,35,63FF |
55 | 2.1.4 | L0DU Simulation | P.Perret | 0 days? | Wed 02-01-30 | Wed 02-01-30 | Wed 02-01-30 | 33 |
56 | 2.2 | L1 | O.Callot | 21 days | Mon 02-04-01 | Mon 02-04-29 | NA | 34 |
57 | 2.2.1 | 2D+3D tracks and vertices | I.Kisel | 10 days | Wed 02-04-10 | Tue 02-04-23 | NA | 63FF |
58 | 2.2.2 | L1Track to L0 Candidate Matching | N.Tuning | 20 days | Mon 02-04-01 | Fri 02-04-26 | NA | 57FF |
59 | 2.2.3 | L1 matching to TT1 | M.Witek | 10 days | Wed 02-04-10 | Tue 02-04-23 | NA | 57FF |
60 | 2.2.4 | L1 Decision (Super L1 FortranNN | N.Tuning | 1 day | Mon 02-04-29 | Mon 02-04-29 | NA | 58 |
61 | 2.3 | Velo | C.Parkes | 15 days | Wed 02-04-03 | Tue 02-04-23 | NA | 35 |
62 | 2.3.1 | Velo RAWH converter | J.Palacios | 1 day | Wed 02-04-03 | Wed 02-04-03 | NA | |
63 | 2.3.2 | Velo Silicon Simulation | 15 days | Wed 02-04-03 | Tue 02-04-23 | NA | 62FF | |
64 | 2.3.3 | Velo Clustering | 15 days | Wed 02-04-03 | Tue 02-04-23 | NA | 63FF | |
65 | 2.4 | IT | M.Needham | 16 days? | Tue 02-03-12 | Tue 02-04-02 | NA | 36 |
66 | 2.4.1 | IT RAWH converter | 1 day? | Tue 02-03-12 | Tue 02-03-12 | NA | ||
67 | 2.4.2 | IT Digitisation and Clustering | 16 days | Tue 02-03-12 | Tue 02-04-02 | NA | 98FF | |
68 | 2.5 | OT | J.v.Tilburg | 15 days? | Tue 02-03-12 | Mon 02-04-01 | NA | 37 |
69 | 2.5.1 | OT RAWH converter | 1 day? | Tue 02-03-12 | Tue 02-03-12 | NA | ||
70 | 2.5.2 | OT Digitisation and clustering | 15 days | Tue 02-03-12 | Mon 02-04-01 | NA | ||
71 | 2.6 | Tracking | M.Merk | 26 days? | Tue 02-03-19 | Tue 02-04-23 | NA | 38 |
72 | 2.6.1 | Stub seeding | R.Forty,R.Hierck | 5 days | Wed 02-03-27 | Tue 02-04-02 | NA | 65FF,68FF |
73 | 2.6.2 | Fast seeding | B.Hommels | 5 days | Wed 02-03-27 | Tue 02-04-02 | NA | 65FF,68FF |
74 | 2.6.3 | Velo Tracking | F.Teubert | 10 days | Wed 02-04-10 | Tue 02-04-23 | NA | 61FF |
75 | 2.6.4 | Track Matching | J.v.Tilburg | 5 days | Wed 02-04-17 | Tue 02-04-23 | NA | 72FF,74FF |
76 | 2.6.5 | Track Following | R.Hierck | 10 days | Wed 02-04-10 | Tue 02-04-23 | NA | 72FF,61FF |
77 | 2.6.6 | Forward Tracking | O.Callot | 5 days | Wed 02-04-17 | Tue 02-04-23 | NA | 74FF,65FF,68FF |
78 | 2.6.7 | Track Fit | O.Callot,J.v.Tilburg | 20 days | Tue 02-03-19 | Mon 02-04-15 | NA | 65FF,68FF |
79 | 2.6.8 | Track Selection ("clone killer") | 1 day? | Tue 02-04-23 | Tue 02-04-23 | NA | 75FF,76FF,77FF,72FF,78FF | |
80 | 2.6.9 | Back Converter to AXAT | C.Jones | 1 day? | Tue 02-03-19 | Tue 02-03-19 | NA | |
81 | 2.7 | RICH | 11 days | Mon 02-03-11 | Mon 02-03-25 | NA | ||
82 | 2.7.1 | Remove ATMC references | G.Wilkinson | 5 days | Mon 02-03-11 | Fri 02-03-15 | NA | |
83 | 2.7.2 | Converters SICB to RichEvent | C.Jones | 10 days | Tue 02-03-12 | Mon 02-03-25 | NA | 39FF |
84 | 2.8 | CALO | V.Belyaev | 1 day? | Wed 02-03-27 | Wed 02-03-27 | NA | 42 |
85 | 2.8.1 | Digitisation and Reconstruction | 1 day? | Wed 02-03-27 | Wed 02-03-27 | NA | ||
86 | 2.8.2 | CaloParticle creator | 1 day? | Wed 02-03-27 | Wed 02-03-27 | NA | ||
87 | 2.9 | Muon | D.Hutchcroft | 29 days? | Thu 02-03-14 | Tue 02-04-23 | NA | 43 |
88 | 2.9.1 | Muon RAWH converter | D.Hutchcroft | 1 day? | Thu 02-03-14 | Thu 02-03-14 | NA | |
89 | 2.9.2 | Muon Digitisation | A.Satta | 14 days | Thu 02-03-14 | Tue 02-04-02 | NA | 88FF |
90 | 2.9.3 | Muon Reconstruction | D.Hutchcroft | 1 day? | Tue 02-04-02 | Tue 02-04-02 | NA | 89FF |
91 | 2.9.4 | Muon PID | Joao | 22 days | Mon 02-03-25 | Tue 02-04-23 | NA | 90FF,79FF |
92 | 2.9.5 | Muon background | 15 days | Wed 02-04-03 | Tue 02-04-23 | NA | 89 | |
93 | 2.10 | Common | 31 days? | Tue 02-03-12 | Tue 02-04-23 | NA | ||
94 | 2.10.1 | Top Level RAWH converters | M.Cattaneo | 5 days? | Wed 02-03-20 | Tue 02-03-26 | Tue 02-03-26 | 27 |
95 | 2.10.2 | MCEvent RAWH converters | M.Cattaneo | 5 days? | Wed 02-03-20 | Tue 02-03-26 | Tue 02-03-26 | 28 |
96 | 2.10.3 | Primary Vertex reconstruction | M.Witek | 31 days | Tue 02-03-12 | Tue 02-04-23 | NA | 74FF,79FF |
97 | 2.10.4 | ProtoParticles creator | G.Corti | 10 days | Wed 02-04-03 | Tue 02-04-16 | NA | 46 |
98 | 2.10.5 | Association tool example and interface | P.Charpentier | 5 days | Thu 02-03-14 | Wed 02-03-20 | NA | 48FF |
99 | ||||||||
100 | 3 | OO-DST prototype | 19 days? | Wed 02-04-03 | Mon 02-04-29 | NA | 25 | |
101 | 3.1 | Definition of content | 2 days? | Wed 02-04-03 | Thu 02-04-04 | NA | 1 | |
102 | 3.1.1 | Event Model Classes | M.Cattaneo | 1 day? | Wed 02-04-03 | Wed 02-04-03 | NA | |
103 | 3.1.2 | Relationship classes | M.Cattaneo | 1 day? | Thu 02-04-04 | Thu 02-04-04 | NA | 102 |
104 | 3.2 | Association tools | 1 day? | Fri 02-04-05 | Fri 02-04-05 | NA | 103 | |
105 | 3.3 | Prototype interface to book-keeping | 1 day? | Wed 02-04-03 | Wed 02-04-03 | NA | ||
106 | 3.4 | Produce 10 events for protoparticle development | M.Cattaneo | 0 days? | Mon 02-04-29 | Mon 02-04-29 | NA | 101,50 |
107 | ||||||||
108 | 4 | OO-DST prototype ready | 0 days | Tue 02-04-30 | Tue 02-04-30 | NA | 1,50,100 | |
109 | ||||||||
110 | 5 | XML geometry and tools | 119 days? | Mon 01-12-17 | Fri 02-05-31 | NA | ||
111 | 5.1 | LHCb-Light geometry defined | 0 days | Fri 02-05-31 | Fri 02-05-31 | NA | ||
112 | 5.2 | Infrastructure | 119 days | Mon 01-12-17 | Fri 02-05-31 | NA | ||
113 | 5.2.1 | Beam pipe | G.Pakhlova | 5 days | Fri 02-05-24 | Fri 02-05-31 | NA | 111FF |
114 | 5.2.2 | Velo exit window | 10 days | Mon 01-12-17 | Fri 01-12-28 | NA | ||
115 | 5.3 | VELO | J.Palacios | 10 days | Fri 02-05-17 | Fri 02-05-31 | NA | 111FF |
116 | 5.4 | IT | Zurich? | 15 days | Fri 02-05-10 | Fri 02-05-31 | NA | 111FF |
117 | 5.5 | OT | Nikhef? | 15 days | Fri 02-05-10 | Fri 02-05-31 | NA | 111FF |
118 | 5.6 | RICH | 64 days | Mon 02-03-04 | Fri 02-05-31 | NA | ||
119 | 5.6.1 | RICH1 | S.Easo | 10 days | Fri 02-05-17 | Fri 02-05-31 | NA | 111FF |
120 | 5.6.2 | RICH2 | A.Papanestis | 20 days | Mon 02-03-04 | Fri 02-03-29 | NA | |
121 | 5.7 | CALO | 1 day? | Mon 02-02-25 | Mon 02-02-25 | Mon 02-02-25 | ||
122 | 5.7.1 | ECAL | G.Pakhlova | 1 day? | Mon 02-02-25 | Mon 02-02-25 | Mon 02-02-25 | |
123 | 5.7.2 | HCAL | A.Berdyugin | 1 day? | Mon 02-02-25 | Mon 02-02-25 | Mon 02-02-25 | |
124 | 5.8 | MUON | D.Hutchcroft | 51 days? | Mon 01-12-17 | Mon 02-02-25 | Mon 02-02-25 | |
125 | 5.9 | Magnetic field service | 1 day? | Mon 01-12-17 | Mon 01-12-17 | NA | ||
126 | 5.10 | Particle swimmer | 10 days | Fri 02-05-17 | Fri 02-05-31 | NA | 112FF,115FF,116FF,117FF,118FF,125FF | |
127 | ||||||||
128 | 6 | Commission algorithms (new geometry etc.) | 56 days? | Thu 02-03-28 | Thu 02-06-13 | NA | ||
129 | 6.1 | L0PuVeto | Nikhef | 1 day? | Fri 02-05-31 | Fri 02-05-31 | NA | 115 |
130 | 6.2 | VELO | C.Parkes | 1 day? | Fri 02-05-31 | Fri 02-05-31 | NA | 115,61 |
131 | 6.3 | IT | M.Needham | 1 day? | Fri 02-05-31 | Fri 02-05-31 | NA | 116,65 |
132 | 6.4 | OT | J.v.Tilburg | 1 day? | Fri 02-05-31 | Fri 02-05-31 | NA | 117,68 |
133 | 6.5 | Tracking | 1 day? | Mon 02-06-03 | Mon 02-06-03 | NA | 130,131,132,71 | |
134 | 6.6 | RICH | 37 days | Wed 02-04-24 | Thu 02-06-13 | NA | ||
135 | 6.6.1 | Tuning to new tracks | G.Wilkinson | 15 days | Wed 02-04-24 | Tue 02-05-14 | NA | 79 |
136 | 6.6.2 | Tuning to new geometry | G.Wilkinson | 10 days | Fri 02-05-31 | Thu 02-06-13 | NA | 118,133FF,81 |
137 | 6.7 | CALO | V.Belyaev | 1 day? | Thu 02-03-28 | Thu 02-03-28 | NA | 121,84 |
138 | 6.8 | MUON | D.Hutchcroft | 1 day? | Wed 02-04-24 | Wed 02-04-24 | NA | 124,87 |
139 | ||||||||
140 | 7 | Commission OO-DSTs | 33 days | Wed 02-05-01 | Fri 02-06-14 | NA | 108 | |
141 | 7.1 | RAW (digi output) | 28 days | Wed 02-05-01 | Fri 02-06-07 | NA | ||
142 | 7.1.1 | Finalise content | M.Cattaneo | 5 days | Wed 02-05-01 | Tue 02-05-07 | NA | |
143 | 7.1.2 | Commission Brunel Digi | M.Cattaneo | 5 days | Mon 02-06-03 | Fri 02-06-07 | NA | 130,131,132,137,138,142,129 |
144 | 7.2 | EOD (reco output) | 33 days | Wed 02-05-01 | Fri 02-06-14 | NA | ||
145 | 7.2.1 | Finalise content | M.Cattaneo | 5 days | Wed 02-05-01 | Tue 02-05-07 | NA | |
146 | 7.2.2 | Back converters for RICH reco | C.Jones | 10 days | Wed 02-05-01 | Tue 02-05-14 | NA | |
147 | 7.2.3 | Test content with physics analysis | G.Corti | 10 days | Wed 02-05-15 | Tue 02-05-28 | NA | 146,145 |
148 | 7.2.4 | Commission Brunel Reco | M.Cattaneo | 5 days | Mon 02-06-10 | Fri 02-06-14 | NA | 143,147,128FF |
149 | ||||||||
150 | 8 | Release Brunel v10r0 | M.Cattaneo | 0 days | Mon 02-06-17 | Mon 02-06-17 | NA | 110,128,140 |