Planing

Time Phase
End May 1999 User requirements (ps, html, pdf)
End June 1999 Database Model (ps, html,pdf)+ system requirements
End August 1999 Prototype
End September 1999 Choice of the model
3rd January 2000 Production phase

Meetings and presentations

The project has been presented during the Software week (June 1999) (ppt, ps).

Minutes of meeting : 16 June 1999 , 29 June 1999, 5 July 1999, 4 august 1999, 6 september 1999


Last edition by Joel Closier :09 November 2005 . This page has been accessed Hit Counter times